What should a business arrange before a commercial EICR?
Agree the installation boundary, gather existing records, identify circuits that affect critical operations and authorise realistic isolation windows. Give the inspector access to boards and relevant spaces, with a named site contact. Plan how urgent findings, unfinished work and restoration checks will be handled before the visit starts.
An EICR project starts before an electrician opens a distribution board. A busy building contains two maps: the electrical circuits on the drawings and the activities that depend on them.
Good preparation brings those maps together. A socket circuit may serve both empty desks and the network cabinet behind a locked door. A short interruption can therefore have consequences that the room name does not reveal. This guide sets out a practical way for facilities teams to commission a useful condition report while keeping decisions, access and disruption under control.
In this guide 5 sections
Read the guide offline or copy its planning points into your own records.
Download this guide as textSet a boundary people can recognise
Write down which buildings, floors, supplies and distribution boards are included. Identify the shared areas and any tenant-controlled installations. Terms such as whole site are too loose when an estate includes separate units, external lighting, a detached store and equipment owned by another organisation.
Ask for the boundary to appear in the quotation and the report. If one supply is excluded, record who will arrange its assessment. This is a purchasing decision with a safety consequence: a complete report for one building does not provide evidence about the untouched building next door.
For a larger project, make a one-page scope matrix with one row per building or supply. Use columns for the responsible party, available records, proposed visit, isolation approval and unresolved questions. Send it with the booking confirmation and review it at the start of attendance. It gives the client and contractor a common reference when a building name, board label or access assumption turns out to differ from the original brief. Keep revisions dated so later readers can see what was agreed.
Assemble a useful information pack
Find the previous EICR with all its schedules, installation certificates for later alterations, board schedules and available drawings. Add a short list of recent changes, recurring trips and known defects. Give each document a date so the inspector can distinguish current information from an old fit-out drawing.
Do not delay reporting a known danger while searching for paperwork. Missing records should be declared rather than reconstructed from memory. Tell the contractor what is unavailable; the inspection plan may need extra circuit identification or investigation time. A candid gap is more useful than an apparently complete but unreliable folder.
Translate operations into isolation windows
Ask department owners which activities need controlled shutdown and restart. Include IT, alarms, access control, refrigeration, production and equipment with timed cycles. A manager saying that the office closes at six does not establish whether a server can be disconnected at six.
In a hypothetical warehouse, lighting can be interrupted after dispatch ends, but the overnight charging area remains active. The testing plan should identify those different conditions rather than reserve one vague evening slot. Electrical isolation and proving dead belong to competent people; the client’s task is to supply operational knowledge and authority.
Give decisions an owner
Nominate a site coordinator who can obtain keys, contact occupiers and approve agreed changes. Also identify the person able to act if the inspector discovers danger. Their role includes arranging safe restrictions or specialist support, not directing the inspector to keep an unsafe circuit running.
Agree the route for a limitation discovered on the day. If a locked plant room is unavailable, who can open it and when? If access cannot be achieved, the report must say what was affected. The choice should be visible while there is still time to resolve it, rather than first appearing in a final PDF.
Plan the handover before the visit
Book time to review the result, observations, schedules and any outstanding areas. Under the current A4:2026 framework, C1 and C2 observations determine an unsatisfactory assessment; C3 and FI have different, advisory roles. Read the report’s declared basis and act on the actual finding, including advice to investigate.
Use this preparation list to turn the booking into an executable job:
- A marked plan identifies each included building and electrical supply.
- Existing reports, alteration certificates and known faults are available.
- Department owners have agreed shutdown and restart arrangements.
- Keys, escorts, safe access and local contacts are booked.
- Urgent findings and changes to scope have named decision makers.
- A review meeting will allocate actions and recover any missing coverage.
EICR testing questions.
Does every commercial site need an EICR every five years?
There is no universal five-year interval in the Electricity at Work Regulations for all commercial premises. Condition, use, maintenance, competent advice and any applicable sector or contractual requirements matter.
Can preparation remove all disruption?
No. Inspection and testing can require isolation. Preparation helps arrange necessary interruptions and identify where phased work or specialist coordination is needed.
Find the relevant service details, access considerations and information to include in an enquiry.
Find inspection advice for your industry →Find your site area →Prepare a site inspection list →Sources used for this guide.
The linked guidance supports the factual context. Check its jurisdiction and the requirements for your actual premises.
- The Electricity at Work Regulations 1989 ↗
Great Britain: duties concerning safe systems, maintenance, isolation and competence. It does not set a universal annual PAT or five-year commercial EICR timetable.
- HSE HSG85: Electricity at work, safe working practices ↗
Supports planning, competence, safe systems of work, isolation and control of work on electrical systems.
- IET: BS 7671:2018+A4:2026 EICR model forms ↗
Primary report structure, extent and limitations, observations, circuit details, test results and recipient guidance. The article explains the form without reproducing it.
- IET Wiring Matters: Further Investigation, July 2026 ↗
Explains the A4:2026 change: C1/C2 determine an unsatisfactory outcome; C3 and FI are advisory. FI still calls for a reasoned investigation response.