Which parts of an EICR should a facilities manager read?
Read the installation details and extent first, then the overall assessment, observations, inspection schedule and circuit test schedules. Check that all pages belong to the same report and cover the commissioned areas. The headline result makes sense only alongside the recorded limitations, findings and recommended next steps.
A long electrical report can feel like a technical appendix with one important word on the front.
That word matters, but it cannot tell you whether the loading bay was included, why a circuit was left untested or which defect needs an urgent response. Reading an EICR well is less about decoding every measurement and more about following its chain of evidence. Start with what the inspector assessed, move to what was found, and finish with the actions and records needed to manage the installation. The current IET model form provides a useful reading order.
In this guide 5 sections
Read the guide offline or copy its planning points into your own records.
Download this guide as textCheck identity and purpose
Confirm the premises, occupier, inspection dates and reason for the report. A report for the landlord’s common areas may have the same postal address as your tenancy while covering a different installation. Match board references against the site records rather than relying on the address alone.
Look for the standard and amendment used. BS 7671:2018+A4:2026 is the current reference after the October 2026 transition, but an older report remains a record of an older assessment. Dates and edition references explain differences in form wording; they should not be silently edited to resemble a new inspection.
Read extent and limitations before the result
The extent describes the included installation. Limitations explain boundaries to inspection or testing, including restrictions agreed beforehand and practical constraints encountered during work. Locate the actual equipment, room or test affected by each entry. A sentence that merely says access restricted is a reason to ask for clarification.
Consider whether the limitation affects your purpose. If the report was commissioned to assess a newly occupied workshop, excluding the workshop supply leaves a significant question unanswered even if the assessed offices are satisfactory. The report can be technically clear and still leave the client with further work to commission.
Turn observations into an action list
Each observation should give enough information to find and understand the issue. Record its reference, board or circuit, location, code, explanation and any immediate action. Ask the inspector to explain uncertain wording in plain language. The code expresses a judgment about the observed condition; it is not a substitute for that condition’s description.
C1 indicates danger present and C2 a potentially dangerous condition. A4:2026 treats C3 and FI as advisory rather than automatic reasons for an unsatisfactory result. Further investigation still needs an owner and a considered response. Historic forms used different FI guidance, so check the report rather than applying a remembered rule.
| A4:2026 observation | Meaning | Management response |
|---|---|---|
| C1 | Danger present | Obtain immediate competent action to remove danger; communicate restrictions. |
| C2 | Potentially dangerous | Arrange urgent competent remedial action and suitable interim control. |
| C3 | Improvement recommended | Consider the recommendation and record the improvement decision. |
| FI | Further investigation advised | Arrange a reasoned response to obtain information needed for a conclusion. |
Make sure the schedules are present
The inspection schedule and circuit details and test results are part of the report’s evidence. They let a future inspector or electrical contractor understand which circuits were assessed, the protective devices recorded and the results obtained. A summary page or invoice cannot replace these schedules.
You do not need to verify electrical calculations yourself. You can check page numbering, consistent report references, recognisable board names and unexplained blanks. Ask what any abbreviation or missing entry means. An applicable test not completed, a test not relevant to that circuit and an overlooked field are three different situations.
Keep a short query list while reading, using page and circuit references. For example, ask whether a blank result represents a non-applicable test or an operational restriction, rather than asking whether the report is complete in general. Specific queries help the inspector answer accurately and give you a written clarification that can be stored with the report for the next team.
Read recommendations as a management task
The proposed next inspection date should relate to the installation and its use, not simply a default calendar setting. Record it with the reason given and review the plan if conditions change. A later inspection date does not mean damage discovered next week can wait until then.
Close the review with a short written decision log. This makes the report useful when the facilities manager, contractor or occupier changes, because the next person can see both the original evidence and the response.
- Confirm every included board can be traced on the site plan.
- Check all referenced schedules and continuation sheets are supplied.
- Allocate each observation and investigation to a responsible person.
- Arrange completion of relevant areas that were not assessed.
- Store the signed report alongside later repair and alteration records.
EICR testing questions.
Is an EICR a certificate for a new installation?
No. It records condition at inspection within its stated extent. Installation work is verified and documented using the appropriate installation certification.
Should I challenge a code I do not understand?
Ask for the defect, location, reasoning and required response to be explained. A commercial decision should be based on a clear finding rather than a code without context.
Find the relevant service details, access considerations and information to include in an enquiry.
Find inspection advice for your industry →Find your site area →Prepare a site inspection list →Sources used for this guide.
The linked guidance supports the factual context. Check its jurisdiction and the requirements for your actual premises.
- IET: BS 7671:2018+A4:2026 EICR model forms ↗
Primary report structure, extent and limitations, observations, circuit details, test results and recipient guidance. The article explains the form without reproducing it.
- IET Wiring Matters: Further Investigation, July 2026 ↗
Explains the A4:2026 change: C1/C2 determine an unsatisfactory outcome; C3 and FI are advisory. FI still calls for a reasoned investigation response.
- IET: Ensure you are up to date with BS 7671 ↗
Confirms A4:2026 is current after the previous version was withdrawn on 15 October 2026; historic reports retain their own declared basis.