Is the overall outcome
satisfactory?
The outcome summarises the condition found within the inspection scope. The observations and recorded limitations explain the detail.
Read any recommendations and the proposed next inspection date. A report describes the installation at the time and within its stated scope.
Under Amendment 4:2026, C1 or C2 observations make the overall outcome unsatisfactory. Ask the inspector to explain the actions, urgency and any immediate measures already taken.
What does the code mean?
Classification is an engineering judgement made by the inspector. This guide does not reclassify observations on your report.
A danger has been identified.
Immediate action is required. The person ordering the inspection should be informed immediately, rather than waiting for the finished report.
Follow the competent inspector’s advice about removing the danger and any restrictions on use.
A condition is potentially dangerous.
Urgent remedial action is required. Ask which circuit or equipment is affected, what work is needed and how it should be prioritised.
A C2 observation makes the overall outcome unsatisfactory.
The issue needs further investigation.
Under Amendment 4:2026, FI advises further investigation and does not itself make the outcome unsatisfactory. Agree what needs investigating and how the result will be recorded.
Do not dismiss an FI observation. Read the inspector’s advice and agree a proportionate response. Earlier report forms may use different wording and outcome rules.
An improvement is recommended.
A C3 observation on its own does not make the report unsatisfactory. Review the recommendation with the inspector and include appropriate improvements in your maintenance planning.
The complete report and any other observations still need to be considered.
Ask for a defined
follow-up scope.
Investigation, repairs and verification serve different purposes. An unsatisfactory EICR does not automatically mean every circuit needs retesting from scratch.
- What exactly was observed?Confirm the location, board or circuit reference and the recorded classification.
- What needs doing and when?Ask for the required investigation or remedial work and the relevant urgency.
- What records will close the action?Agree the appropriate certification or verification evidence after work is completed.
- What is excluded?Review limitations and any parts of the installation not included in the inspection.
How long is an EICR valid?
The next inspection interval depends on the installation, use, condition, maintenance and external influences, as well as relevant obligations. The competent inspector records a recommendation; a single interval should not be assumed for every commercial property.
Keep the report and the follow-up together.
Retain the EICR, agreed investigation or repair scope and resulting records. Give the responsible site or property contact access to the information needed to plan maintenance and future inspections.