EICR codes explained.Understand the findings.

Read C1, C2, FI and C3 in context, then work out which questions to ask about the report and any follow-up.

Illustration of a commercial electrical cabinet, test instruments and report-review materials
Report findings, explainedREACTION / GUIDES
Start with the report

Is the overall outcome
satisfactory?

The outcome summarises the condition found within the inspection scope. The observations and recorded limitations explain the detail.

SATISFACTORY

Read any recommendations and the proposed next inspection date. A report describes the installation at the time and within its stated scope.

UNSATISFACTORY

Under Amendment 4:2026, C1 or C2 observations make the overall outcome unsatisfactory. Ask the inspector to explain the actions, urgency and any immediate measures already taken.

Select a classification

What does the code mean?

Classification is an engineering judgement made by the inspector. This guide does not reclassify observations on your report.

C1 / IMMEDIATE ACTION

A danger has been identified.

Immediate action is required. The person ordering the inspection should be informed immediately, rather than waiting for the finished report.

Follow the competent inspector’s advice about removing the danger and any restrictions on use.

Before commissioning work

Ask for a defined
follow-up scope.

Investigation, repairs and verification serve different purposes. An unsatisfactory EICR does not automatically mean every circuit needs retesting from scratch.

  1. What exactly was observed?Confirm the location, board or circuit reference and the recorded classification.
  2. What needs doing and when?Ask for the required investigation or remedial work and the relevant urgency.
  3. What records will close the action?Agree the appropriate certification or verification evidence after work is completed.
  4. What is excluded?Review limitations and any parts of the installation not included in the inspection.

How long is an EICR valid?

The next inspection interval depends on the installation, use, condition, maintenance and external influences, as well as relevant obligations. The competent inspector records a recommendation; a single interval should not be assumed for every commercial property.

Keep the report and the follow-up together.

Retain the EICR, agreed investigation or repair scope and resulting records. Give the responsible site or property contact access to the information needed to plan maintenance and future inspections.

For an existing report, provide the observations and any work already completed. Do not use this guide to diagnose or repair an electrical installation yourself.
Current classification context: IET Amendment 4 explanation ↗IET edition and transition checker ↗
Quote enquiry

Request an EICR quote

Add a circuit estimate and testing window, or start with the report you already have.

No contact details needed for these first questions.Prefer to talk? 0203 885 2299