Remedial work creates a new event in an installation’s history. The property record should show what the inspection found, what was authorised and how the later work was verified.

Request an EICR quote
The short answer

What evidence should be retained after electrical remedial work?

Retain the original inspection report, the authorised work scope and evidence appropriate to what was actually done. That may include an Electrical Installation Certificate, a Minor Electrical Installation Works Certificate, relevant test records or a defined maintenance or investigation record. Link the evidence to the original findings and preserve unresolved matters. Do not silently rewrite the earlier report as if its original condition never existed.

An invoice marked complete rarely explains all three. This article gives commercial buyers a practical way to assemble the evidence after repairs or investigation, without demanding the same certificate for every task. It also addresses a common temptation: replacing the earlier report with a cleaner-looking file and losing the original findings. Clear links between records usually serve the maintenance team better than an unexplained change of status.

In this article 6 sections
  1. Agree the evidence while defining the work
  2. Read the work description, not just the certificate heading
  3. Use a finding-to-evidence register
  4. A repair package is complete, but its investigation is not
  5. Preserve the original report and control later issues
  6. Keep historic FI findings and current duties clear
01

Agree the evidence while defining the work

Before instruction, identify each finding the proposed work is intended to address. Separate defined repair, investigation and optional improvement. Ask the competent contractor what certification, testing or other record is appropriate to each activity and include the agreed handover in the order.

The nature of the work determines the evidence. New circuits and more extensive installation work need different consideration from qualifying minor alterations, routine maintenance or investigation. Avoid choosing a document solely because it is familiar to procurement. A clear scope lets the electrical people identify the appropriate verification, while the buyer can check that the delivered pack corresponds to what was authorised.

02

Read the work description, not just the certificate heading

The IET’s current forms provide for installation certification and minor works certification, with stated boundaries. Check that the supplied document identifies the premises, work completed and relevant installation or circuit references. Retain its associated schedules or results where applicable; a cover page alone may leave the technical record incomplete.

A minor works certificate is not a universal repair receipt. Its suitability depends on the task, and the IET’s notes exclude new circuits and certain replacements from that form’s scope. Where the activity was maintenance or investigation, ask for a record that describes the work, findings and relevant verification. The absence of a familiar form title does not justify accepting no meaningful evidence at all.

03

Use a finding-to-evidence register

A short register helps a coordinator review a mixed package without altering the original technical documents. Preserve the report’s observation reference and connect it to the authorised work and completion information. If one work item addresses several findings, make that relationship explicit. If a finding remains partly unresolved, keep the remainder open.

Register fieldWhat to recordReview question
Source findingReport reference, observation and installation location.Can another reviewer find the original concern?
Authorised workThe accepted scope and any approved changes.Does the completion record describe that work?
Completion evidenceRelevant certificate, results or task record and issue reference.Is the evidence appropriate and complete for the activity?
Review decisionWho checked the evidence and what was concluded.Is closure supported rather than merely asserted?
Outstanding matterRemaining investigation, access or remedial decision.Who owns the next step and what information is needed?
04

A repair package is complete, but its investigation is not

Imagine a hypothetical office commissioning socket repairs and investigation of an unidentified circuit. The invoice describes the whole order as complete. The pack contains evidence for the socket work and a note that tracing could not be finished because another occupier’s area was unavailable.

Link the socket evidence to the relevant findings and review it appropriately. Keep the circuit investigation open, recording the restriction and the access decision needed. Ask for clarification if the note does not explain what was established. Paying the order or closing the contractor attendance does not resolve the outstanding technical question. The register should tell the next coordinator why one group of actions is closed and another still requires work, without relying on memory of the visit.

05

Preserve the original report and control later issues

The earlier EICR records an assessment at the time of its inspection. Retain it alongside the later work evidence rather than deleting observations or changing its date locally. If an authorised correction or later report is issued, identify its reference, purpose and relationship to the earlier record. A new document should be understandable as a new issue or event, not a silent replacement of history.

Whether another condition inspection is needed depends on the circumstances and purpose. Do not assume either that every repair demands a full repeat EICR or that later work can never create another inspection need. Seek competent advice about unresolved findings, altered extent and verification requirements. A customer, insurer or contract may also have a specific evidence requirement that should be clarified explicitly.

Store the completed pack where the people responsible for maintenance can find it. Include the original report, approved scope, relevant completion evidence and the action review. Update changed circuit or asset information through the appropriate process so the next inspection starts with useful records. Keep any outstanding limitations visible during property or contractor handover.

06

Keep historic FI findings and current duties clear

Read a historic EICR using its declared edition and recipient notes. Under the IET’s A4:2026 reporting change, C1 and C2 determine an unsatisfactory outcome, while C3 and FI are advisory classifications; the FI wording now advises further investigation. Do not silently recode an older report or remove an outstanding question from the action register because the current model form uses different wording.

An advisory report classification does not remove a separate duty to investigate. Current government guidance for qualifying private and social rented homes in England still addresses necessary investigative and remedial work and the associated written confirmation. Those residential rules must not be turned into a blanket 28-day deadline for every commercial installation. Establish the applicable duties, report recommendations and contractual requirements, then agree the investigation, repair and completion evidence appropriate to the actual finding. Keep unresolved matters open until the evidence supports closure.

Related questions

EICR testing questions.

Should the original EICR be changed to remove repaired observations?

Do not edit it locally or erase its history. Retain the original and link appropriate later evidence. Any authorised revision should be clearly identified and controlled.

Does every remedial job need another full EICR?

Not automatically. The work and remaining questions determine appropriate verification and any further inspection. Confirm the evidence needed with competent people and check specific contractual requirements.

Research & further reading

Sources used for this article.

The linked guidance supports the factual context. Check its jurisdiction and the requirements for your actual premises.

  1. IET: BS 7671:2018+A4:2026 Electrical Installation Certificate ↗

    Certification of defined installation work and its associated responsibility and verification records.

  2. IET: BS 7671:2018+A4:2026 Minor Electrical Installation Works Certificate ↗

    Appropriate use, exclusions and retention guidance for minor works evidence.

  3. IET: BS 7671:2018+A4:2026 Electrical Installation Condition Report ↗

    Condition reporting context; the finding-to-evidence register is an editorial management recommendation.

  4. HSE: Maintaining electrical equipment safety ↗

    Maintenance to prevent danger, informed by equipment, environment and previous checks.

  5. IET: Further investigation, July 2026 ↗

    Current A4:2026 outcome and advisory-classification distinction.

  6. GOV.UK: electrical safety standards in private and social rented sectors ↗

    Sector-specific England investigative/remedial duties; not a blanket commercial timetable.

Inspection service

EICR testing: scope & records.

See what the service includes and which site details help prepare a relevant quote.

View the service details
Quote enquiry

Request an EICR quote

Share the original report references and proposed work so the required scope and reporting handover can be clarified.

No contact details needed for these first questions.Prefer to talk? 0203 885 2299
Call the teamGet a quote